Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Test bed is currently still under modification
Risk reduction tests are still being conducted for temperature uniformity
Flow analysis may be conducted
Accomplishments from Previous Week
Heat sensor risk reduction for temperature uniformity
Technically, compact fan heater is sufficient for heating needs
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Modify test bed setup to allow for more turbulent and/or stronger airflow for temperature uniformity
Validate a proof of concept design from risk reduction
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Add more annotations to photos of the stage controller for clarity
Will be taken into consideration in next ppt presentation
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Try to use more 3D printed parts for testing to save time
Test bed incubator and housing elements are 3D printed for now
Test for temperature uniformity with an assortment of thermocouples/sensors
Risk reduction was run with 9-10 thermocouples to test for consistency
Can a test be run to see if the stage controller concept works?
Risk reduction test was run with multiple thermocouples and a compact fan heater
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
More explanation/clearer labeling of diagrams and setup
Allocate more time/go more in-depth with slides
Increase visibility and decrease word density on slides
Reiterate the importance of the stage controller
Risks and Areas of Concern
Openings in the bottom of the enclosure due to gaps in specimen adapter
Complications related to pressure of air flow due to tubing
Resources or Information Required but not Available
How to use flow simulations in CAD
Schedule
Find efficient method to distribute temperature within the enclosure uniformally
Simulations and/or additional tests
Validate proof of concept
Budget (list amount spent and amount remaining)
Amount Spent:
To date: ~$375
Amount Remaining:
Highest Possible (assuming $5000 reserve): $4625
Lowest Possible (assuming $3000 reserve): $2625
Progress on Report and Webpage
Working on Applicable Standards section (Draft due Friday 4/27/18)
Webpage is still being updated