Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Finished and assembled heat-treated components
Machining Aluminum I-beams and brackets
Accomplishments from Previous Week
Machined and assembled test bed
Received heat-treated parts and assembled yoke
Machined all base-plate 8020 pieces (cuts and holes)
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Machine mounting holes on main I-beam tower, mount to base frame (Josiah)
Machine mounting holes and brackets for smaller base I-beams (Matthiew)
Complete facing of all I-beams and machine pulley shaft key way and through hole (Bryant)
Complete machining and tapping spring plates, assemble guide assembly (Ian)
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
none
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
none
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
none
Risks and Areas of Concern
Machining and assembling on time
Resources or Information Required but not Available
none
Schedule
Machine and assemble major components
Budget (list amount spent and amount remaining)
Spent: $3058.80
Remaining: -$58.80
**We are waiting on student discount credit for certain purchases, ~$80
Progress on Report and Webpage
Report: Finished 2nd Draft, will polish based on feedback
Webpage: Periodically adding updated work