Overview of Status of Analysis, Design, Fabrication, Tests, etc.
All subassemblies fully designed, most built, minor modifications needed for optimal functioning
Code works well to drive each independent motor, now integrating in actual control logic
Accomplishments from Previous Week
Conveyor belt built and motorized
Folding Mechanism jaws attempted to motorize (simple fix inbound, interior mounting hole dimensions were incorrect)
Impulse Sealer Housing built and attempted to motorize (simple fix inbound, gear ratio not currently enough)
Dispensers motorized
Cutter production begun, prototype built, issues categorized and fixes inbound
All motors now successfully driven and all subassemblies sans cutter have been tested with their motors, fixes for issues are inbound
Impulse Sealer Housing attached to Conveyor Belt, along with Folding Mechanism
Brainstorming mounting techniques for dispensers
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Get everything we need done by FRIDAY!
Finish modifications to Driving Solutions for Impulse Sealer Housing and Folding Mechanism (Griffin)
Finish assembling all subassemblies into one final assembly (Griffin)
Insert Impulse Sealer Circuit into Housing (Ali)
Test full system and work on optimization (Jerry)
Make sure cutter works reliably (Dai)
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
N/A
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Report needs some work (5/23)
Cutting will not be as easy as we think (5/23)
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
N/A
Risks and Areas of Concern
Time (as always!)
Resources or Information Required but not Available
N/A
Schedule
Team Meeting with Sponsor soon
Want final design 100% ready to show sponsor by end of week (Namely 6/2)
Poster Draft by Midnight of 6/2
Update Gantt chart accordingly
Budget (list amount spent and amount remaining)
No money spent last week, still at $35.93 (last week's slightly different value based on just an estimate for shipping, current values reflect charged values).
Progress on Report and Webpage
Website beautified
Second pass on Report finished
Still collecting final images and data for both