Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Still in design phase
Accomplishments from Previous Week
Found risk reduction tests
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Design concepts 1 per team member
Finish risk reduction tests; test the wheelchair on different types of terrain
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments
His concern for using on sand--we chose a risk reduction test to see what the wheelchair is capable of
Instructor Comments from Last Meeting and Actions Taken to Address these Comments
n/a
Risks and Areas of Concern
Safety of sponsor
Resources or Information Required but not Available
n/a
Schedule
Risk reduction test Week 10
Budget (list amount spent and amount remaining)
Spent: $0
Amount remaining: $4000
Progress on Report and Webpage
no access yet