Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Individual Analysis of Components ongoing
LED circuit design in progress
Accomplishments from Previous Week
Risk Reduction test completed and successful.
Presentation completed
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Finish Individual Component Analysis (Simon, Jen, Noor, Nick)
Finalize designs for LED circuit
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Might not be able to use incubator because of sterility concerns (3/14/14 - in person)
new designs solutions being looked at including the use of delta pads for temperature control
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Risk reduction test in incubator to see effects of heat dissipation in incubator ( 3/13/14 - in person)
Couldn't test inside the incubator itself because of sterility issues and other experiments inside incubator, but could use walk-in incubator for risk reduction test
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
N/A
Risks and Areas of Concern
Maintaining Constant Temperature 33-39 degrees C
Heat Dissipation from LEDs
Resources or Information Required but not Available
N/A
Schedule
Describe upcoming milestone
Update Gantt chart.
Budget (list amount spent and amount remaining)
$ 0 spent
$ 3000 remaining
Progress on Report and Webpage
Updated week 10 Progress Report