Overview of Status of Analysis, Design, Fabrication, Tests, etc.
The sealant was applied onto the prototype. Newly modified parts of the prototype are designed and will be cut out.
Will start testing by as early as possible.
Testing on sealant has been done and successful.
Accomplishments from Previous Week
Lasercammed new modified parts
From last week's assembly, we discovered some modifications is neededÂ
Applied sealant to prototype
Sealant was applied to areas where they are difficult to access by using syringe.
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Jasmine - Finish report
Paul - Finish assembly
Jordan - Prototype Testing with Paul
Tommy - Begin working on poster
Will - Help with assembly & edit website
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Will be meeting this week to test out product with sponsor to receive feedback on improvements
The sealant is taking longer than expected to dry, which delays the assembly.
Some modifications were made to the prototype and will be lasercammed this week.
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Commercializing/Patent issue
Our sponsor has thought for possible future commercial use with our project. This brings up the patent issue.
Drainage design
Have the drain on the side of the reservoir rather than at the bottom.
This will eliminate problem of uneven bottom surface.
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
None
Risks and Areas of Concern
All previous concerns have been addressed, now just need approval of a successful prototype from sponsor.
Resources or Information Required but not Available
None
Schedule
Finish full assembly this week (Week 8)
Start & complete testing this week (Week 8 ~ 9)
Continue working on report and finish full draft by the end of the week (Week 8)
Budget (list amount spent and amount remaining)
$74.86 has be spent on materials to date with a remaining $425.14 left within our budget.
Progress on Report and Webpage
Report is near completion (for first full draft)
Need to update front page & contacts page of website still.