Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Overall design completed
Currently in fabrication & testing mode
Working on report
Working on website
Accomplishments from Previous Week
Cut out acrylic parts
3D printed chamber (but not reservoir)
Tested waterproofing/ sealant
Started on first draft of report
completed abstract, chapter 1, executive summary
Determined usability of sealant
Applies well with sponge (and not the brush)
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Jasmine
Continue working on the first draft of the report
Check to see objective platform to see if there are any holes to secure screws into
Jordan
Buy tubing
Determine tubing specification
Edit first draft of report
Paul
Assemble prototype together
Test prototype
Work on website
Will
Assemble prototype together
Test prototype
Work on website
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Design looks good
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
In person, April 22, 2013
Look into pressure release valve for the pump so the tube doesn't pop
Not necessary because the pump will be a syringe.
Another type of coating available at Home Depot for $15 - $20 incase our current sealant doesn't work
What kind of o-ring are we using?
rubber o-ring from McMastercarr. Dimensions have yet to be determined.
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
None
Risks and Areas of Concern
None
Resources or Information Required but not Available
None
Schedule
Describe upcoming milestone
Update Gantt chart.
Budget (list amount spent and amount remaining)
Bought
Silicone o-rings
Total spent for the week: $12.99
Total spent to date: $54.58
Amount remaining: $445.42
Progress on Report and Webpage