Overview of Status of Analysis, Design, Fabrication, Tests, etc.
An analysis using FEMAP is being conducted for our sponsor meeting on Wednesday
The frame design is complete with the base and middle support rung to be designed
The fabrication of the prototype is being completed this week after the materials are delivered
Load testing on the clamps and legs will be completed this week to test for clamp slip and buckling
Accomplishments from Previous Week
Final Design proposal
Purchased multiple clamp designs for prototyping and testing
Modeled the design proposal with FEMAP
Placed a purchase order request for aluminum tubing to manufacture a full scale leg prototype
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Fabricate telescoping leg with both 1/8" and 1/16" wall thickness
Perform a load test to determine if 1/16" wall thickness can satisfy the strength requirements
Test the clamps
Fabricate 1" diameter clamp out of aluminum
Use FEMAP to analyze the model with the help of ATA sponsors
Place an order for all tubing materials
Test and comparison of Locktite, JB Weld and Epoxy
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Prefer to use standard epoxy over JB weld
Use loctite for small bond lines
Use a ratchet strap as a base rather than a steel cable
Doesn't have to fit within the given sizing constraints if we can pack 4 units in the shipping crate successfully
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
Use of Bike Lever Clamps
Ratchet straps instead of clamps at each joint
Risks and Areas of Concern
The 1/16" wall thickness may be subject to denting
The clamps may have to be fabricated as opposed to being purchased off the shelf
The weight of the off the shelf clamps may cause us to go over the weight restriction
Slip due to vibration excitation
Resources or Information Required but not Available
Schedule
Week 3 - Receive order tubing.
April 15 - Meet with Professor
April 17 - Meet with sponsor
April 17 - Finish preliminary FEMAP analysis
April 18 - Finish Leg fabrication
April 18-19 - Testing
April 19 - Decide on final specs for legs (wall thickness and diameter)
April 19 - Place full order of materials for the fabrication of one unit.
Budget (list amount spent and amount remaining)
$110 (Tubing)
$55 (Clamps, JB Weld) Probably Returning
Remaining: $1335
Progress on Report and Webpage
Report layout posted and shared on google docs
Title Page, Background, Existing Solutions, Deliverables, Statement of Requirements