Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Design reworked and improved. Fabrication of major components complete, assembly of major components started.
Accomplishments from Previous Week
Fabrication of parts begun.
Covering design finalized and ready for 3D printing.
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Finalize frame order (Randy)
Covering 3D print (Chase)
Electronics setup (Chris)
Finish Crank and Coupler components (Brian)
Full Unit assembly (Team)
Begin Poster and Finish Rough Draft (Meagan)
Testing
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments
3d Printing has been approved and will be started this weekend
Instructor Comments from Last Meeting and Actions Taken to Address these Comments
Motor spec analysis approved, motor ordered.
Presentation created showing comparisons between 4Bar and Slider Crank synthesis.
Risks and Areas of Concern
Electronics
Resources or Information Required but not Available
Low budget ordering
Schedule
Testing phase upcoming.
Budget (list amount spent and amount remaining)
$1300 spent
$1200 remaining
Progress on Report and Webpage
Report Rough Draft 2 nearly complete.
Webpage updated as per TA comments.