Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Final actuation design is underway, covering design is nearing completion and ready for printing.
Accomplishments from Previous Week
Yokes have been machined and assembled. Leg linkages nearing completion.
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Finish and order materials for machine housing. Randy
Finish covering, place 3D print order. -Chase
Machine and assemble actuation system. -Brian/Meagan
Motor spec, sensor decisions. -Chris
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments
Damon would like us to present our current status at DJO headquarters. We have tentative plans to do so next Monday.
Instructor Comments from Last Meeting and Actions Taken to Address these Comments
Finish analysis and order motor ASAP. Motor analysis is complete, it initially appears that we can snag a motor off mcmaster-carr if we become desperate.
Risks and Areas of Concern
Covering compatibility with design.
Motor size/spec
Resources or Information Required but not Available
3D Cad model of bracing products. Will have to create our own if necessary for solidworks analysis.
Schedule
Full assembly of the knee cycle tester linkages should be complete by next week.
Update Gantt chart.
Budget (list amount spent and amount remaining)
Spent ~$300
$2200 remaining
Progress on Report and Webpage
Report rough draft 1 has been turned in and is awaiting feedback.
Webpage is current with recent design solutions uploaded.