Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Leg fully assembled and covered, it meets the full expected range of motion with no bracing collapse points.
Power supply and electronics 90% complete, force sensor to be installed.
Accomplishments from Previous Week
Complete leg assembly!
power supply complete, all actual outputs meets expectations
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Finish Electronics - Chris
Finish Arduino Program - Meagan
Frame and Casing touch up - Brian, Randy, Chase
Finished KCT : Team
Report Final Draft - Team
Poster Final Draft - Team
Webpage Final draft - Brian
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments
Meeting time set, sponsor is impressed with the covering and leg so far.
Instructor Comments from Last Meeting and Actions Taken to Address these Comments
Deadlines set, detailed gantt chart made.
Risks and Areas of Concern
May not be able to get a full cycle test in and "break" a knee brace in time
Resources or Information Required but not Available
--
Schedule
Meeting with DJO next week.
Poster Presentation next week (finals)
Budget (list amount spent and amount remaining)
~$2000 SPENT
~$500 REMAINING`
Progress on Report and Webpage
Report final draft corrections are under way.
Poster rough draft to be reviewed
Webpage needs some adjustments. (Front page and executive summary need updated)