Lag - The amount of time whereby a successor activity will be delayed with respect to a predecessor activity.
Lead - The amount of time whereby a successor activity can be advanced with respect to a predecessor activity.
Lead Time - The time between a customer request and the actual delivery.
Lessons Learned - The knowledge gained during a project, which shows how project events were addressed or should be addressed in the future, for the purpose of improving future performance.
Lessons Learned Register - A project document used to record knowledge gained during a project, phase or iteration so that it can be used to improve future performance for the team and the organization.
Life Cycle - See project life cycle