TASK 1
DATE OF UPDATE: July 16, 2019
TASK: Purchase all the required materials
RESPONSIBLE: Rish Sangar
DUE: July 22, 2019
TASK 2
DATE OF UPDATE: July 16, 2019
TASK: Cut and assemble all the components to form the machine box.
RESPONSIBLE: Rish Sangar
DUE: July 27, 2019
TASK 3
DATE OF UPDATE: July 16, 2019
TASK: Assemble and Test the machine.
RESPONSIBLE: Rish Sangar
DUE: July 29, 2019
TASK 4
DATE OF UPDATE: July 16, 2019
TASK: Prep the Final report and Presentation
RESPONSIBLE: Rish Sangar
DUE: August 01, 2019
TASK 1
DATE OF UPDATE: OCT 03, 2019
TASK: Finish Scope Statement Package
RESPONSIBLE: Rish Sangar
DUE: OCT 04, 2019
TASK 2
DATE OF UPDATE: OCT 21, 2019
TASK: Practice on Surface models in Solidworks
RESPONSIBLE: Rish Sangar
DUE: OCT 21, 2019