According to an email with the new project manager on July 11, 2023 the timeline for the rest of development goes as followed:
Predesign: 5/16/23 – 3/1/24
Design: 7/5/23 – 3/1/25
Construction: 2/14/25 – 1/29/28
The final EIS was released. You can view it here.