Transportation

Capital Improvement Projects

S. Lakeshore Drive/Summit Ridge Drive Reconstruction

(From SH 66 to FM 740)

Project Manager: Jeremy White, P.E., CFM

Construction Inspector: James Palmer

Current Status: Under construction

Project Scope:

  • Roadway reconstruction with sidewalks
  • Alley reconstruction (certain alleys)
  • Water line replacement
  • Wastewater line replacement
  • Storm drainage improvements
  • See Project Location Map – Blue highlighted alleys
  • Project Schematic

Project Update:

  • Temporary Northbound One-Way Traffic
    • Starting Monday, March 2, 2020 one-way westbound traffic will begin for Summit Ridge Drive. The section between S. Alamo Road and Ridge Road (FM 740) will remain open to two-way traffic. Traffic will continue one-way north bound on S. Lakeshore Drive. Please seek alternate route during this phase of construction. See Map for detour route.
  • Last Month’s (January) Activities:
    • S. Lakeshore Drive (West side of road [southbound])
      • Continued one-way road northbound (from S. Lakeshore Dr./Summit Ridge Dr. intersection to SH 66)
      • Continued work to cut new road grade and place new sub-grade for roadway pavement.
      • Continued placing steel and forms for new concrete pavement.
      • Continue pouring main lane pavement from Shoreview Dr. to bridge at SH 66.
      • Continue channel erosion protection under bridge at SH 66.
    • Summit Ridge Drive
      • Began water line installation.
    • Stonebridge Drive/Shoretrail Drive
      • Finished pouring remaining driveways.
      • Lay sod and final clean up work.
  • This Month’s (February) Activities: (weather permitting)
    • S. Lakeshore Drive (West side of road [southbound])
      • Pour paving for intersections and alley approaches.
      • Continue channel erosion protection under bridge at SH 66.
    • Summit Ridge Drive (North side of road [westbound])
      • Continue water line installation.
    • Stonebridge Drive/Shoretrail Drive
      • Work substantially complete.
  • Next Month’s (March) Activities: (weather permitting)
    • S. Lakeshore Drive (West side of road [southbound])
      • Finish out pouring paving for intersections and alley approaches.
      • Finish channel erosion protection under bridge at SH 66.
      • Prepare to move traffic on to new paving (west side) – Traffic to remain northbound one-way
    • Summit Ridge Drive (South side of road [eastbound])
      • Continue water line installation.

County Line Road Reconstruction

(Horizon Road to Renee Drive)

Project Manager: Jeremy White, P.E., CFM

Construction Inspector: Steve Salazar

Current Status: Under construction

Project Scope:

  • Roadway reconstruction with sidewalks
  • Water line adjustments
  • Wastewater line adjustments
  • Storm drainage improvements

Project Update:

  • Last Month’s (January) Activities:
    • North side of the road - FM 3097 (Horizon Road) to Eva Place.
      • Substantially complete on this section and side of road.
    • South side of the road - FM 3097 (Horizon Road) to Eva Place.
      • Work on concrete driveways, sidewalk, guardrail, and pedestrian rail on top of retaining wall.
    • South side of the road - East of Ranch Trail to Renee Drive.
      • Began clearing trees at edge of right of way.
      • Began installation of new water line and storm drainage lines.
  • This Month’s (February) Activities: (weather permitting)
    • FM 3097 (Horizon Road) to Eva Place.
      • Substantially complete on this section.
    • East of Ranch Trail to Renee Drive - South side of the road.
      • Continue installation of new water line and storm drainage lines.
  • Next Month’s (March) Activities: (weather permitting)
    • FM 3097 (Horizon Road) to Eva Place.
      • Work on final clean up items.
    • East of Ranch Trail to Renee Drive - South side of the road.
      • Continue installation of new water line and storm drainage lines.
      • Prepare for pavement subgrade treatment.

Highland Drive Reconstruction

( Bedford Falls Lane to Valley Drive)

Project Manager: Jeremy White, P.E., CFM

Project Scope:

  • Roadway reconstruction with sidewalks
  • Water line replacement
  • Wastewater line replacement
  • Storm drainage adjustments

Phase 1 - Bedford Falls Lane to Driftwood Drive

    • Current Status: Complete

Phase 2 - Driftwood Drive to Valley Drive

    • Current Status: Engineering design. No construction anticipated at this time.

Alta Vista Drive Reconstruction

(from N. Lakeshore Drive to Westway Drive)

Westway Drive Reconstruction

(from Carriage Trail to Highland Drive)

Carriage Trail Reconstruction

(from Aspen Court to Alta Vista Drive)

Aspen Court Reconstruction

(from Highview Lane to Carriage Trail)

West Street Reconstruction

(West Drive: Highland Drive to W. Rusk Street)

Project Manager: Jeremy White, P.E., CFM

Current Status: Engineering design (anticipated completion Spring 2020)

Project Scope:

  • Roadway reconstruction
  • Water line replacement
  • Wastewater line replacement
  • Storm drainage improvements

Project Update:

Ridge Road West Reconstruction

( from Shores Blvd to N. Goliad St. (SH 205))

Project Manager: Jeremy White, P.E., CFM

Current Status: Engineering design (topographic & ROW survey) no construction anticipated at this time (design only)

Project Scope:

  • Roadway reconstruction
  • Storm drainage improvements

Project Update:

Woodpark Drive Reconstruction

(Spring Creek Drive to S. Alamo Road)

Lakedale Drive Reconstruction

(Lakeview Drive to Ridge Road)

S. Lakeshore Drive Reconstruction

(2000 Block)

Project Manager: Jeremy White, P.E., CFM

Current Status: Engineering design (topographic & ROW survey) no construction anticipated at this time (design only)

Project Scope:

  • Roadway reconstruction
  • Water line replacement
  • Wastewater line replacement

Project Update:

Turtle Cove Blvd Reconstruction

(Ridge Road to Railroad Tracks)

W. Yellow Jacket Lane Reconstruction

(from Ridge Road to Greencrest Blvd)

Project Manager: Jeremy White, P.E., CFM

Current Status: Engineering design (topographic & ROW survey) no construction anticipated at this time (design only)

Project Scope:

  • Roadway reconstruction
  • Storm drainage adjustment

Project Update:

S. Lakeshore Drive Reconstruction

( Summit Ridge Drive to Tanya Lane)

Russwood Drive Reconstruction

( S. Lakeshore Drive to Spring Creek Drive)

Project Manager: Jeremy White, P.E., CFM

Current Status: Engineering design (topographic & ROW survey) no construction anticipated at this time (design only)

Project Scope:

  • Roadway reconstruction
  • Water line replacement
  • Wastewater line replacement
  • Storm drainage improvements

Project Update:

N. Alamo Road Reconstruction

( Live Oak Street to Downtown Couplet)

Project Manager: Jeremy White, P.E., CFM

Current Status: Engineering design (topographic & ROW survey) no construction anticipated at this time (design only)

Project Scope:

  • Roadway reconstruction
  • Storm drainage improvements

W. Boydstun Avenue Reconstruction

( Forest Trace to N. Goliad St. (SH 205))

Forest Trace Reconstruction

( S. Lakeshore Drive to W. Boydstun Avenue)

Project Manager: Jeremy White, P.E., CFM

Current Status: Engineering design (topographic & ROW survey) no construction anticipated at this time (design only)

Project Scope:

  • Roadway reconstruction
  • Water line replacement
  • Wastewater line replacement
  • Storm drainage improvements

Project Update: