Total anticipated: 5 years
Annual task breakdown
Year 1 ('22):
Form & organize committee
Research project background
Outreach for historical imagery
Analyze outdated cost estimate
Send RFQ/RFP to design firms
Year 2 ('23):
Choose Design Firm
Pre-design survey & report
Launch dedicate website
Phase-1 programming & schematics
Year 3 ('24):
Revise budget parameters
Comprehensive travertine study
Hire Project Manager
Send RFP to General Contractors
Build preliminary global schedule
Year 4 ('25):
Onboard General Contractor
Phase-2 design development for build
Finalize two schemes incl. materials
Primary survey & report
Build model floor
Order bulk materials
Begin construction
Year 5 ('26):
Complete construction