Visit us at our temporary location inside the lobby of the Giddings Economic Development Corporation at 924 E. Austin St. M-F 10A-6P, SAT 10A-1P.
Monday, April 6, 2026: Flooding is found in various areas of the library. The cause is determined to be a broken pipe that dumped 500 gallons of water into the library. Several areas within the library are affected. Initially, we expect a week-long closure.
Week of April 6, 2026: During clean-up, asbestos is found beneath the old carpet. The asbestos must be abated, and the insurance company determines that all carpet in the main library area needs replacing. Expected closure time: three months. The building is expected to reopen mid-July.
Week of April 13, 2026: To ensure the safety of library visitors and staff, the City decides to abate all asbestos and replace all carpeting not covered by insurance. Considerable funds are saved by adding the additional reconstruction to the current project instead of completing it as a separate project. Because only a small portion is not covered by insurance, there is no additional closure time expected.
Monday, April 20, 2026: We announce the opening of a temporary, teeny-tiny library inside the lobby of the Giddings Economic Development Corporation.