Progress Update:
Sitework
South parking lot entrance complete
85% of North parking lot installed, North entrance complete
75% of site has received topsoil
Site electrical/water main/storm and sanitary sewers installed
Area A (NW Classroom Wing)
Roofing Complete
First and second floor concrete installed
Second floor framing is 75% complete
Second floor Mechanical/Plumbing/Electrical Rough ins are progressing
Started framing on the first floor
Exterior brick veneer is being installed
Area B (SW Classroom Wing)
Structural steel framing complete
Roof and second floor metal decking installed
Portion of roofing insulation has been delivered to the site
Area C
Gym roof trusses installed
Upcoming Project Milestones:
Area A (NW Classroom Wing)
Start second floor drywall installations the week of 11/23
Window delivery 12/9
Complete exterior brick veneer the week of 11/16
Area B ( SW Classroom Wing)
Start roofing the week of 11/9
Place second floor and first floor concrete
Area CÂ
Balance of project structural steel delivers on 10/30
Erect remianing structural steel