September 16th, 2019
CPP GLJC Developments requesting proposals from Design-Build Companies Schematic Design, Design Development, Construction Documents, and Construction of a 14-Story Office Tower in Irvine, CA
September 16th - November 8th, 2019
Led by Design:
Every week, Denalo Engineering would meet with the Owners in order to plan the phases of the projects in a manner that meets the Owner's vision.
November 18th, 2019
Submitted: Technical Proposal with Staff, Relevant Projects, Architectural, Geotechnical, Structural, Project Schedule, Site Logistics, Risk Register, LEED, and Lump Sum Cost
November 19th & 20th, 2019
Denalo Engineering presented themselves and their proposal submittal to the Owner’s. The Owner’s will choose the best company via the Best Value Selection
December 13th, 2019
Denalo Engineering was selected to complete the design, construction and maintenance of the project
January 27th, 2020
Led by Construction:
Every week, Denalo Engineering would meet with the Owners in order to plan the construction development phase
March 6th, 2020
During the Construction Devlopment phase, our team was notified of a necessary change order that required us to make design changes as well cost and schedule changes.
April 24th, 2020
This was the date we had all our work finalized and began focusing on our Industry Presentation on May 1st, 2020
May 1st, 2020
The Denalo Engineering Team presented our Senior Project via Zoom Conference Call. The presentation was set to a 30 minute maximum with a 10 minute Q & A period.