Gantt Chart
Milestones
1. Obtain MSW
-Define source and potential types of plastic to be tested
- Descreiption on website page
2. Determine best motor and coupling
-Discuss electronics with Dr. Farmer
-meet with Mick about what is available
-decide on parts & write up more in depth process flow
3. Determine supplementary parts
-Determine all rotating parts for shredder; gears, coupling, etc.
4. Build shredder
- work with initial shielding
- Image of shredder built
5. Plastic testing
- Determine size output from shred
-Allowable plastics
- Present data on milestone page
6. Integration
-Making all moving parts connect, no automationneeded yet
-Ensure safety of use
- Image, possibly video.
-Discuss hazard points and how to fix.
7. PLC justification
- What PLC to use and logic diagram (flow chart) & pseudocode
8. Automation of machine
- PLC working correctly
-Machine is fully automated
9. Testing of microplastic
- Measure contents in wastewater after passing through membrane
- Web page of data
10. Final manual
- How to use/ safety
Responsible Parties:
Lilly and Abbey
Abby and Lilly
Lilly and Johnna
Abbey and Abby
Abby and Johnna
Lilly and Abbey
Johnna and Abbey
Johnna and Abby
Lilly and Abbey
Abby Lilly