July 2023 Update :
Phase 2 of the project is underway.
Phase 2 consists of the following:
ADA upgrades which were completed Summer 2022
Renovation of Cafeteria - Finishing bathroom accessories, Installing kitchen equipment, Installing flooring, Painting.
Addition of Gymnasium - Installing Gym equipment, Installing panels on exterior walls.
Final cleaning, Sidewalks and Landscaping & Inspections.
All work is progressing well with Phase 2 anticipated completion in Sept 2023. The school remains operational without interruptions with ongoing daily coordination between school staff and the construction team. The construction site is fully secured and separated from school operation making the construction possible while school is in session.
Phase 3 of the project construction commencement is on Hold until further notice.
Please direct any questions or concerns to (401) 889-4811.