Milestones:
March 28, 2014 - Pleasanton Weekly - "Remaking History" article
December 17, 2013 - Pleasanton Heritage Preservation Award!
June 17, 2013 - Garage final inspection complete!
April 20, 2013 - We moved In !!!!
April 17, 2013 - House final inspection complete!
April 4, 2013 - Permit pulled for two-car detached garage
April 1, 2013 - Interior Hardwood floors, carpets, appliances, final electrical and plumbing in the works
March 5, 2013 - Cabinets delivered ... Interior trim work in progress ... Interior prime coat completed... Exterior initial color coat completed
February 15, 2013 - Exterior exterior paint prep and primer completed, interior "old world" wall texture completed.
February 7, 2013 - Exterior carpentry complete, including all front restored Victorian detail - ready for paint
February 2, 2013 - Drywall install and Inspection complete, Trex deck and front stairs complete
January 29, 2013 - Insulation install and inspectioncomplete
January 23, 2013 - Electrical. plumbing, HVAC rough inspection complete
January 15, 2013 - New roof and electrical rough-in complete
January 12, 2013 - Plumbing rough-in complete
January 9, 2013 - All-wood window install complete (Jeld-Wen)
January 4, 2013 - French drains & Basement waterproofing done
December 4, 2012 - Foundation complete- Framing begins
October 30, 2012 - New Foundation begins
October 24, 2012 - House move begins
October 16, 2012 - Demolition started
October 16, 2012 - Construction Begins!
October 9, 2012 - Building Permit secured
October 9, 2012 - Selected Contractor - V. A. Tragni, Inc.
October 4, 2012 - Construction Plans approved by Pleasanton Building Dept
August 28, 2012 - Construction Plans out for Contractor bids
August 28, 2012 - Plans submitted to City of Pleasanton Building Dept (Plan Check)
August 24, 2012 - Plans approved by City of Pleasanton Planning Dept
July 11, 2012 - Final plans submitted to City of Pleasanton Planning Dept
June 1 - June 27, 2012 - Plans submitted for Preliminary Planning Review - City of Pleasanton
May 31, 2012 - Land survey completed - Darryl Alexander
April 23, 2012 - Selected Architect - Terry Townsend
March 27, 2012 - Heritage Tree removal and Walnut tree trimming completed - Highland Tree Service
March 16, 2012 - Purchase complete - deed recorded
March 16, 2012 - Property Purchased!