A Logic Network shows the sequence of activities in a project across time. It indicates which activity logically precedes or follows another. Create a Start (left) and End (right) sticky note and put them on a whiteboard. Arrange the WBS sticky notes in the logical sequence of activities from left to right. Join the notes with an arrow in and out; some may have more than one arrow. All connecting lines on a network enter at the left (beginning) of the activity box (sticky note) and exit at the right (ending). Lines do not enter the top or exit the bottom of the activity box. Unconnected lines are not allowed. All activities must connect to another activity or the start or end of the project. Write the time every activity will take on each sticky note to calculate the project duration. Once completed, you have created a Logic Network that will help you understand the dependencies in your project, timescale, and its workflow. This technique can reveal valuable information that might otherwise get overlooked.