Unpermitted structures are fairly common in California. Most often these structures are patios, outdoor kitchens/BBQs, ADUs/accessory structures like garages, HVAC, MPUs and roofs. There are some things you should be mindful of here:
Typically and in the vast majority of cases most AHJs and inspectors stance is as long as we are not touching the structure (no electrical nor solar mounted on it in any way) the AHJ/inspector will let this slide/look the other way. Meaning we can get our solar done and get to PTO and there is no reprecussions to us nor the homeowner.
Although this is typical it is NOT always the case meaning some AHJs and/or inspectors will create an issue for us and/or the homeowner if they see anything unpermitted. This could be in the form of failing our inspection(s) and/or opening an enforcement case against the homeowner.
Ultimately this is primarily an inspector discretion issue meaning the inspector makes the final call. There are AHJs where some inspectors will create an issue but other inspectors will not inside of the same AHJ.
There are times where the AHJ will let our solar go to PTO and then will open an enforcement case on the homeowner, this is rare but it does and can happen. Typically if we are allowed to go to PTO the inspector will not create an issue for the homeowner but again not always.
We get permits before doing solar and many times the AHJ will issue us a permit and then will catch this at inspection. Countless times we have had permits issued and then fail inspection due to an unpermitted structure we had listed on the planset that the AHJ issued a permit for. Sometimes they will not issue us a permit due to an unpermitted structure which allows us all to dodge the bullet but this is NOT always the case.
When there is an inspection failure due to an unpermitted structure we:
Try and work with the AHJ to see if and how we can resolve this.
Work with you as the rep and the homeowner as needed to try and resolve the unpermitted structure. Sometimes the homeowner can work with the contractor that did this work to get it permitted, inspected and compliant to solve this issue.
Work with a new contractor (at a cost) to resolve this issue and some times this is virtually unresolvable.
Each case is unique and different and one size does not fit all.
BE CAREFUL - keep in mind if we fail an inspection due to an unpermitted structure and it is not resolved in a timely manner and we get clawed back by the financing company we will also need to claw back your commission as well too. Once resolved and we are paid in full (post final funding) we will repay your commission 100% as long as we are ultimately paid in full. If we are not paid in full there may be some impact to your commission. Again each case is unique.
REMEMBER - we are partners. Just like you want this to go final funding its not nearly as much as we want this to go to final funding. Although getting your commissions clawed back is painful and something we want to avoid this is 3-5X more painful for us as we have not just invested a ton of time in this project just like you but we also have hard costs (materials, labor, permitting, design, etc. etc. etc.)