Sales Reps, this is your chance to level up! Our new video reveals game-changing insights to supercharge your performance at Skyline. Discover how our rapid installations and streamlined processes can help you close deals faster and earn more. Learn from our leadership’s proven experience and get insider tips on design, permitting, and scheduling that will keep your pipeline moving. Master how we drive installers to deliver on time and navigate inspection and PTO delays like a pro. This is your opportunity to dominate the field—watch now and elevate your success to new heights!
Table of Contents
Skyline's background: Founded 25 years ago, initially a security company, expanding into solar in 2018.
Focuses on speed and efficiency for both installs and customer satisfaction.
Aims to achieve 30 days from sale to installation and 60-90 days for PTO (Permission to Operate).
The company does about 100 solar installs per month, primarily in California.
Recent growth has resulted in 250,000 lifetime security installs and nearly 5,000 solar installs.
Speed to install is key for earning commissions and customer satisfaction.
Homeowners start saving money immediately after PTO is approved.
The company prioritizes quick installations to meet customer expectations and fulfill commitments.
System activation begins immediately upon PTO approval, with no payment due until 30-60 days after PTO approval.
Experienced leadership: The leadership team has extensive solar experience, starting from entry-level roles.
Skyline’s leadership comprises individuals who have worked in various roles from installation to project management.
Hands-on experience: The leadership team, including the president, has personally been involved in sales, design, engineering, and even installation.
This ensures a deep understanding of daily challenges in solar installation and sales.
The leadership team focuses on fostering a culture of quality and fast service throughout the company.
Survey to design: After a sale, surveys are typically completed the next day, followed by design within a few days.
Designs go through a thorough QA process with over 85 checkpoints to ensure quality and accuracy.
The company uses a third-party service, Aurora, for design but plans to in-source design to improve speed and control in the future.
Permitting is generally fast, with the advent of online permitting tools (like Solar App) speeding up the process.
However, delays can happen due to AHJ (Home Jurisdiction) processes and issues with permitting.
Clean pipeline management: If a project faces issues, the sales team is notified immediately, and the job is put on hold to resolve any concerns.
The company avoids scheduling jobs more than two to three weeks out to ensure commitment and avoid customer forgetfulness. This strategy helps to maintain efficient scheduling and reduce customer complaints.
When delays occur, Skyline prioritizes rescheduling quickly and informing, both the customer and sales representative.
Internal communication: Sales reps are updated on any issues via text message notifications, ensuring full transparency.
Installers are compensated based on job completion and quality to incentivize timely, high-quality work.
Install timeframes: Most installations are completed in one day, with only 5-15% requiring additional time.
Skyline tracks install completion rates, with around 90% of installs meeting the scheduled timeframe.
When jobs go beyond scheduled time, customer satisfaction can suffer due to missed appointments or rescheduled installations.
Installers face penalties if jobs are delayed, ensuring they are motivated to finish on time.
Inspection delays: Fire inspections, particularly in regions like LA County, can take 30-45 days, extending the overall PTO process.
Final inspections may require an additional two weeks to complete, pushing out the PTO timeline.
Permitting revisions: Sometimes permits need to be revised after installation adding delays to the process.
Skyline uses a manual process to track rejections and identify causes of delays to prevent future issues.
PTO approval: Utility companies often have a significant influence on the timeline, with some approvals taking several weeks.
MPU (Metering Point Upgrade): Skyline avoids doing the MPU before the solar install to mitigate potential issues with the roof or other parts of the installation.
The process of getting MPU approval can take months in some areas, especially when working with difficult utility planners.
PTO submission is typically immediate after installation, but approval times are heavily dependent on the utility company.
NorCal PG&E is one of the faster utilities, completing PTO approvals within one to two weeks.
LA County has one of the slowest PTO timelines, with processes taking up to 100 days from install to PTO.