Tasks
Task 1. Test/calibrate the monitoring network and implement FAS operational software (complete DPS4D installations/ operators training).
Task 2. Establish bistatic HF propagation links between participating DPS4D ionosondes
T2.1. Make oblique ionogram measurements
T2.2. Make FAS observations using the DPS4D built-in FAS measuring software
T2.3. Oblique ionograms and FAS data files accessible through GIRO
Task 3. Analyze FAS measurements
T3.1. Setting up the analysis methodology.
T3.2. Process the measurements using the FAS analysis software.
Task 4.Test the extensive capability of FAS measurements
T4.1. Validate the results of the FAS analysis software
T4.2. Study possible coupling of FAS results with other electron density reconstruction models.
Task 5. Collect users' requirements for the warning system
Task 6. Implement the warning system according to the end-users requirements - perform an overall assessment of the system's performance