1- Check revision of isometric & P&ID
2- Check P&ID for how many boundaries
3- Arrange groups same number of boundaries
4- Request piping & pipe support material
5- Compare spool vs last rev. isometric
6- Report shortage
7- Check dimension, weight, location & welding map
8- Pipe support erection possibility
9- Arrange transportation & lay down place
10- Arrange scaffolding
11- Arrange all required tools
12- Arrange man power
13- Arrange crane according to point 4
14- Start fit up & checks alignment
15- Arrange welders & riggers
16- Check related test pack
17- Consider safety requirements all the time
18- Make records for all letters, RFI & NCR
19- Make records for all material requests
20- Make record for the daily progress
21- Make record of welding map
22- Check foundation, level & access of erection