January
- Machine Shed Office
- Framed walls
- Installed I-joists to support upper deck storage area
- Installed staircase & railing
- Installed bi-fold door hardware & fixed door strike plate & broken door jamb
- Replaced light switch & removed kitchen vent hood
February
- Basement
- Repaired several damaged drywall areas & applied orange peel texture
- Primed drywall repairs
- Installed base board
- Repaired kitchen & bathroom drawer
- Installed bathroom vanity light fixture
- Installed bedroom ceiling fan
- Installed towel bar & shelving unit
- Replaced 2 door knobs
March
- Machine Shed Office
- Installed & mud & taped drywall
- Applied crow's foot texture on ceiling & orange peel texture on walls
- Installed & trimmed out doors
- Basement
- gutted basement down to bare studs
- rewired the entire basement (2 bedrooms, living room, & bathroom) under the supervision of a licensed electrician
April
- Machine Shed Office
- installed door, wainscoting, chair rail, base board, extension jambs for windows, casing for windows & doors
- Basement
- built custom built-in desk/bookshelf
May
- Basement
- installed door casing, base board
- installed outlets, light fixtures, switches, & smoke detectors
- installed toilet & sink/vanity
June
- Dock extension
- built a 4' x 12' deck to extend from the shore of a lake to the dock
- provided the ability to have the dock sit further into the water so the boat was in deeper water
- Basement remodel - 2 bedrooms
- installed 4 recessed can lights
- hung drywall
- Basement Bathroom
- replaced a cracked porcelain sink bowl
- installed new faucet & drain assembly
- Horse Barn renovation
- disassembled a wooden shelving unit that was previously installed in the room & retrofitted it in another location
- installed custom saddle, horse blanket, & accessory racks
- built a custom storage cabinet
July
- Replaced a ripped screen on a screen door
- Installed 2 universal window well covers
- Textured 2 ceilings to cover up a popcorn textured ceiling
- Installed an LCD TV mounted on a swivel wall bracket & added a coax cable line & outlet
- Adjusted gutters that were sagging on a garage
August
- Basement Bathroom Finishing
- Installed peel & stick vinyl tile flooring
- Installed shut off valve & toilet
- Installed 6 cabinets
- Cut & installed 2 laminate counter tops
- Installed shut off valves & 2 sinks
- Installed 3 light fixtures
- Built a custom corner cabinet for storage & to hide a HVAC duct that came down through the drop ceiling
- Installed an interior door & casing
- Installed base throughout the room
- Installed accessories (towel hooks & bars, paper holder, door handles, drawer pulls, mirrors)
- Installed vinyl shutters on a house
- Re-installed & adjusted a bi-fold closet door
- Installed a sliding glass patio door
September
- Removed an old ceiling fan & replaced it with a new unit
- Removed an old entry door in a log cabin & replaced it with a new unit
- Repaired a toddler bed
- Helped a friend install decorative wall paneling in barn loft
October
- Skylight cover up
- Homeowner had recently re-roofed the house & had removed 2 skylights
- Installed insulation & framing
- Hung drywall, mud & taped, & textured ceiling
- Adjusted a out of plumb storm door & installed weather stripping
- Basement Remodel
- Basement had open ceilings & finished walls in living room & play room
- Installed 18 recessed can lights
- built soffit in the play room
- Installed drywall, mud & taped, & textured ceilings
- Painted ceilings
- Installed cove moulding
- Installed suspended ceiling & light fixture in bathroom
- Installed suspended ceiling & light fixture in the hallway
- Installed an LCD TV on a wall mount & wired a surround sound system
- Garage trim
- Installed casing on 2 doors
- Built Azek jamb extensions for 3 windows & installed them with casing
- Installed Azek jambs & casing for a 9 foot, interior garage door opening
November
- Installed soffit vents
- Built a custom changing table & storage shelves in a bedroom closet
- Adjusted an exterior door that had sagged
- Installed 2x2 framing on basement block walls prior to spray foam insulation being installed
- 12x12 Deck Extension
- augered holes & poured concrete footings
- attached ledger board to the house
- framed deck, homeowner will install deck boards next Spring
- Installed 9000 square feet of drywall in a 2-story 4 bedroom, 3 bath house that had been gutted
December
- Installed 3 flood lights on the exterior of a house
- Replaced a laminate countertop in a basement wet bar area & plumbed in a sink with new shut-off valves
- Basement Renovation
- framed walls & soffits
- pulled wire for lights & outlets
- installed drywall
- mud/taped/textured drywall