Through the calibration process, which includes the calibration, of this final product and the range of motion shown in the videos, the spine phantom satisfies all project constraints. More information is detailed in the Final Report.
Engineering Days (E-Days) is a chance for all senior design teams to showcase each and every year-long project to industry members and the public. With this year being a virtual E-Days due to COVID-19, a digital poster has been provided that was used during judging.
Note: The videos in the "Final Design" section can be seen above.
Final showcase of our work to Medtronic personnel. Presented to Medtronic Restorative Therapies Group located in Louisville, CO on 4/16/20.
Risk Assessment of final design performed from January through April 2020. There is a noticeable trend of decreasing risk as more development has been made with the spine phantom.