Engineering and Design Docs
PPPL Engineering Procedures for Design, Procurement, Fabrication, Procedures, T-Mods (Links Below)
Posted 7/22/19PPPL Engineering Procedures for Design, Procurement, Fabrication, Procedures, T-Mods (Links Below)
Lab-Wide QA and ES&H Procedures (Links Below)
Posted 7/22/19Lab-Wide QA and ES&H Procedures (Links Below)
Project Plans
Posted 7/22/19Project Plans
Project QA Plan
Posted 7/22/19NSTX-U-QAP-001-02 NSTX-U QA Plan.pdf
Project Chit Tracking Plan
Posted 7/22/19NSTX-U-PLAN-003-01 CHIT Tracking Closure Plan.pdf
Project FO Plan
Posted 7/22/19NSTX-U-PLAN-001-00 Fabrication Oversight_Plan_R1.pdf
NSTX-U Recovery Design Materials
Posted 7/24/19NSTX-U Recovery Design Materials
Integration Reviews
Posted 7/22/19Integration Reviews
TF Bundle Review #2 Report
Updated 7/24/19TF Bundle Review #2 Report
2nd Review of NSTX-U TF Bundle Insulation - final v1.pdf
Design Reviews by Work Breakdown Structure (WBS)
Updated 7/24/19Design Reviews by Work Breakdown Structure (WBS)
WBS 1.1 TORUS SYSTEMS
WBS 1.1 TORUS SYSTEMS
WBS 1.1.1 - PFCs
- PFC Low Heat Flux PDR (9/29/17)
- PFC High Heat Flux PDR (11/15/17)
- PFC FDR (9/28/2018)
- CSFW/CSAS Peer Review (5/1/19)
WBS 1.1.2-Vacuum Vessel and Internal Hardware
- Polar Region-Inner PF Coil Supports PDR (3/27/18)
- Passive Plates & He Line Repair CDR (6/8/18)
- Passive Plates & He Line Repair PDR (7/26/18)
- Polar Region-Flanges PDR (8/2/18)
- HTP HTT PDR (11/30/17)
- VVIH Field Scope PDR (2/23/18)
- TF OH / Casing Trial Fit FDR (4/17/18)
- CSC Modification PDR (10/16/18)
- CSC FDR (12/28/18)
- PF-4/5 Realignment CDR (10/25/18)
- Metrology Mount FDR (11/26/2018)
- HTP HTT FDR (11/1/2018)
- PF-4/5 Realignment Peer Review (5/31/19)
- PF-4/5 Realignment PDR (7/10/19)
- Machine Core Structures FDR (8/5/19 & 8/6/19)
- PF-4/5 Realignment FDR (8/9/19)
- Passive Plate & He Line Repair FDR (8/21/19)
WBS 1.1.3 - Magnets
- Inner PF Coil PDR (12/14/17)
- Cooling Water System Interlock PDR (2/22/18)
- Inner PF Coils FDR (3/30/18)
- Outer PF Coil Inspection / Repair PDR (3/13/18)
- TF/OH Bundle Reliability PDR (4/3/18)
- Inner PF Prototype Coil Power Test FDR (5/9/18)
- Inner PF Water Fitting FDR (1/4/19)
- PF Bus Work PDR (2/28/19)
- TF Inner Bundle Review #1 (4/9/19)
- TF Sample Fabrication Peer Review (4/17/19)
- TF Inner Bundle Review #2 (8/7/19 & 8/8/19)
WBS 1.3 AUXILIARY SYSTEMS
WBS 1.3 AUXILIARY SYSTEMS
WBS 1.3.1 Bakeout
- HTHS Feedthrough PDR ()
- Gas Piping PDR (1/11/18)
- Ex-VV Heating System PDR (2/1/18)
- Bakeout DC Connection PDR (4/5/18)
WBS 1.3.3 Vacuum and Fueling
- Interspace Pumping PDR (12/20/17)
- Interspace Pumping FDR (2/20/19)
- Private Flux Region Mechanical PDR (04/19/19)
WBS 1.4 PLASMA DIAGNOSTICS
WBS 1.4 PLASMA DIAGNOSTICS
- PFC Diagnostics PDR (1/4/18)
- Machine Instrumentation PDR (3/22/18)
- PFC Diagnostics FDR (3/29/2019)
WBS 1.5 POWER SYSTEMS
WBS 1.5 POWER SYSTEMS
- PF1B Power Circuits PDR (2/27/18)
- PF1B Bipolar Circuit FDR (9/20/18)
- Breaker Upgrade/Refurbishment FDR (7/12/2019)
WBS 1.6 CENTRAL I&C
WBS 1.6 CENTRAL I&C
No Recovery Project Design Reviews
WBS 1.8 SITE PREPARATION / ASSEMBLY
WBS 1.8 SITE PREPARATION / ASSEMBLY
- NTC Shielding PDR (8/6/18)
- Machine Reassembly PDR (8/1/18)
- Test Cell Radiation Annunciator & O2 Monitoring PDR (8/14/18)
- NTC Shielding FDR (1/14/19)
- Test Cell Radiation Annunciator FDR (2/12/19)
WBS 1.9 Site Preparation and Assembly
WBS 1.9 Site Preparation and Assembly
WBS 1.09.02 NSTX-U Reassembly
- Reassembly PDR (8/1/19)
WBS 1.09.04 NSTX-U Personell Protection System
- PSS CDR (12/13/2018)
- PSS Requirements Peer Review (5/8/19)
- PSS PDR (6/26/19)
WBS 1.10
- Shorted Turn Protection CDR (5/9/2019)
Maintenance and Run Preparation Reviews
Maintenance and Run Preparation Reviews
- TVPS Backing Pump PDR (9/29/17)
- CAMAC Phase 1 PDR (2/16/18)
- GDC Anode PDR (4/19/18)
- Bakeout PLC Upgrade PDR (5/10/18)
- GDS Expansion Tank Burst Disc FDR (5/29/18)
- CAMAC Replacement FDR Phases 1 & 2 (6/26/18)
- CAMAC Replacement Pilot FDR Phase 3 (6/6/18)
- SAD-2 FDR (12/14/2018)
- TVPS Backing Pump FDR (1/12/19)
- NTC Network Expansion (CWDM) FDR (6/24/2019)