Note: The Recovery Project is funded from NSTX-U operations.
[9/30/19] CDE-2 Baseline Approved and CD-3A long lead procurements approved: letter link
[6/9/20] CDE-3B Balance of Project approved: letter link
[2/28/21] Proposed Revised Baseling Submitted to DOE
"Resnapped the line" based on December 2020 close.
One-Day Director's Review [2/28/21]: link
This baseline was tracked internally, but not accepted by DOE.
Description of Proposed Revised Baseline: link
[3/1/22] Baseline reset in anticipation of rebaseline review in spring 2022
"Resnapped the line" based on February 2022 close - call this the February 2022 Baseline.
Note: DOE has been generous in providing bridge authorization to support the Project after exceeding the CDE-2 TPC