Our Progress

As a project that is receiving a grant from the Massachusetts School Building Authority (MSBA), the project needs to follow the prescriptive process and timeline required by the MSBA. Our project is currently in MSBA Module 3: The Feasibility Study. The timeline below outlines the different steps for each MSBA module.

MODULE 1: Eligibility Period

March 2022 – June 2023







MODULE 2: Forming the Project Team

July 2023 - March 2024



MODULE 3: Feasibility Study

Estimated: April 2024 – April 2025






< We are here 


MODULE 4: Schematic Design

Estimated: May 2025 – December 2025



Module 5: Funding the Project

Estimated: January 2026 – May 2026



MODULE 6: Detailed Design 

(If Project is Approved at 2026 Town Meeting)

Estimated: June 2026 - June 2027 (Approximate)



MODULE 7: Construction 

(If Project is Approved at 2026 Town Meeting)

Estimated: July 2027 – August 2029 (Approximate)



MODULE 8: Completing the Project / Project Closeout 

(If Project is Approved at 2026 Town Meeting)

Estimated: September 2029 – December 2030



MODULE 9: Post Occupancy Evaluation 

(If Project is Approved at 2026 Town Meeting)

Estimated: September 2032 – January 2033 (Process starts three years after building occupancy)