AUGUST 1, 2024 UPDATE
Progress is moving forward very nicely at the New Valley Middle School. The concrete footings and foundations are going in and will be completed soon. We have received 4 truckloads of structural steel and are planning to start setting the steel towards the middle of August.
The precast walls are scheduled to start going up in the middle of August as well. Plumbers and electricians have been on site completing underground work within the building.
TIME LAPSE VIDEO | VMS PROGRESS | UPDATED: AUGUST 23, 2024
https://drive.google.com/file/d/1_wGGIeJxUTuYgUeDEAJNFBPuuhttWVtg/view?usp=sharing
PROGRESS PHOTOS | VMS, AUGUST 1, 2024
https://drive.google.com/file/d/1kNc1eC1oXN4W95RbBXqoXgFxQMGH9S7y/view?usp=sharing
Renderings of the future VMS