CONTROL/SECURE ENTRANCES UPDATE | AUGUST 1, 2024
The Access Controls project will be wrapped up before school starts this fall. This project includes replacing all of the back-end equipment as well as all the door readers and intercom devices on the schools. This equipment update will allow all buildings to be on one system for easier control for modifications and adjustments to the district as a whole.
Design is continuing on all of the school projects currently. EAPC Architects is currently wrapping up construction documents for Red River High School, which will be the first project that will be starting, and construction is expected to begin this fall and continue during the winter months wrapping up early in 2025. Summer of 2025 will be busy with multiple projects finishing design in early 2025 with construction scheduled to start on a most of the Tier 1 schools next summer as soon as students are out if not sooner if constructability allows.