AUGUST 23, 2024 UPDATE:
COMPLETED WORK | LAST 2 WEEKS:
The Central Kitchen project is moving forward nicely. The curb and gutter around the site and garage addition slab was completed this week. Roofing activities were finished last week on the addition and in the existing building. Inside the building, drywall hanging and taping was completed, and we are starting to paint in the offices. Mechanical ductwork, overhead plumbing and electrical work is ongoing.
WORK IN PROGRESS:
Addition: We are currently setting the joist and decking on the garage addition.
Existing Building: We are currently finishing drywall installation and taping.Mechanical ductwork and overhead mechanical/electrical/plumbing (MEP) work is ongoing.
INTERIOR PROGRESS PHOTOS
EXTERIOR PROGRESS PHOTOS