September 2021

Week of August 30-September 2, 2021

In the photos to the right you will see the carpenters framing out corridors and classrooms on 2nd floor. In addition, the second photo shows the masons are laying up block walls at stage area. Lastly, the caulking contractor is installing the air barrier and caulk on the building envelop.


Week of September 6-10, 2021

Arrowhead Forward Update: In picture one, the crane is picking up the roof top unit and the hvac equipment as it curbs to the roof in preparation for start of our roofing installation in the upcoming weeks.

In the second picture you will see metal stud framing and dense glass sheathing. This work will continue as the construction team works to establish the building envelope.

In the third and final picture this week, Masonry Contractors continue their work in gym area laying concrete masonry units to complete partition walls to their full height.

Video of the gym, stage, main entrance, admin, and classrooms

Week of September 13-17, 2021

Arrowhead Forward Update: In picture 1, you will see the southwest corner of the classroom wing. The brick veneer is beginning to be laid as various stages of the building envelope are displayed.

In picture 2, you will see the roof drain piping installation is underway in locations which will be above ceilings or in walls.

In picture 3, ironworkers are welding some of the last remaining pieces of structural framing left on the building at what will be the main entrance into the new building.


Video of the library, hallway, and classrooms

Week of September 20-24, 2021

Arrowhead Forward Update:

In the first picture below, you will see the brick veneer being constructed and extending skyward at one stairwell.


In the second picture, you will see a grease interceptor set and connected to the building plumbing system.


The third and final picture shows the under slab conduit roughed in to convey all wiring and cabling to the main distribution frame of building.