February 2022

Week of January 31-

February 4, 2022

In picture 1, you will see the lobby work in progress. The staircase base is to be poured this week.


In picture 2, you will see the domestic piping installation in the Custodial Closet


In picture 3, you will see the drywall installation in the 2nd floor corridors.


Week of

February 7-11, 2022

In picture 1, you will see the Site Contractor digging a trench for the new gas service piping.


In picture 2, you will see a first glimpse of the metal wall paneling installed on the building exterior.


In picture 3, you will see the painter has applied primer and the first coat of paint to the finished classroom walls.



Week of

February 14-18, 2022

In picture 1, you will see newly installed gas train with meters ready for connection by the Plumbing Contractor.

In picture 2, you will see the Painting Contractor has begun to spray block filler in Cafeteria.

In picture 3, you will see Carpenters hanging and finishing gypsum board in Library and Art Room areas



Week of

February 21-25, 2022

In picture 1, you will see the clerestory area in Library with light diffusing glass now installed.


In picture 2, you will see the exterior of clerestory with metal panel installation complete, the window trim and roofing installations continues toward completion.


In picture 3, you will see TV Studio with 1st coat of green screen paint applied to the interior wall.