SHARK-NIR arrived at the main bay of the LBT Observatory, then moved into the clean room, in the clean tent.
At the end of the Pre-Com-1 the instrument was parked outside the clean room.
Instrument internal alignment: checked
Instrument internal performance: checked
Phase diversity for NCPA correction performance: checked
Internal cleaning of the instrument: done
SHARK-NIR team on the mountain: Jacopo Farinato, Luca Marafatto, Maria Bergomi, Elena Carolo, Simone Di Filippo, Marco Dima, Davide Greggio, Davide Ricci, Gabriele Umbriaco, Daniele Vassallo.
Checking the movement of the internal motors of SHARK-NIR.
After re-wiring the instrument in the clean tent, the correct operation of the motorized part inside the instrument was checked.
Each filter and coronagraphic masks wheel, the motors insert the internal calibration fibers, the mirror deployer for the flat field source and the deployer of the pupil lens work correctly.
SHARK-NIR ready to be moved to the clean room
SciCam installation in the clean room
Instrument internal cleaning
Instrument tested and parked .. ready for the next pre-com run!
SHARK NIR installation at the telescope: done
Alignment of SHARK-NIR to the telescope using ARGOS light source: done
SHARK-NIR team on the mountain: Jacopo Farinato, Luca Marafatto, Marco Dima, Davide Greggio, Luigi Lessio, Davide Ricci, Gabriele Rodeghiero.
TT loop tests: done
NCPA characterization: almost done
SHARKNIR - TCS test: done
SHARK-NIR team on the mountain: Jacopo Farinato, Luca Marafatto, Elena Carolo, Daniele Vassallo.
A. Cavallaro photo