Working on final report
Waiting on data to be processed
Presented at the Undergraduate Research Conference (URC)
Completed Proof of Concept Presentation
Completed first draft of Final Report
Draw conclusions from processed data
N/A
N/A
Congratulations on the URC presentation
Take a breather, and oragnize for next week
N/A
Make Slides Less Cluttered
Streamlined presentation slides
Percent ablation of each rod during each exposure
All information has been provided or able to be found.
Upcoming Milestone: Revise Final Report
Budget ~ $2,000
$205 per rod
$425 per port
Quoted from Machine shop