Finalizing revisions on first draft of IMECE paper
First day of experiments completed, second day of experiments happening next week
Preparing first draft of Final Report
1st day of DIII-D experiments was successful
Submit IMECE paper
Present at Undergraduate Research Conference (URC)
Present Proof of Concept Presentation
Great effort making the IMECE paper happen.
Submitted the IMECE paper
The URC had an available spot for 2 members to present, Asked if we would be inclined to participate in the event.
Caitlin and Daniel said they would present on behalf of team
Preparations to present begin
N/A
N/A
Performance of the rods in the second day of experiments
Risk of disruption from carbon impurities
All information has been provided or able to be found.
Upcoming Milestone: Conduct second day of DIII-D experiments.
Budget ~ $2,000
$205 per rod
$425 per port
Quoted from Machine shop