Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Arrival of parts:
Power Supply
Batteries
Bluetooth Module (HM-10)
Testing of commercial Peltier device to begin soon
Accomplishments from Previous Week
Completed procedures for testing of commercial Peltier device
Updated code to prepare for testing of commercial Peltier device
Acquired battery for final prototype
Determined how to connect microcontroller to mobile app and acquired necessary hardware
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Troubleshoot controller code after testing (Justin)
Purchase RTDs?
Figure out how to implement code for RTDs to replace thermistors (if we decide to get RTDs) (Justin)
Test battery and implement bluetooth components to existing prototype [Hardware] (Tom)
Communicate successfully with micro controller through app (Kam)
Figure out components to use for the RLC filter (Jeffrey)
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
None
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Use shunt resistor to measure current (In person, 4/06/20)
Look at previous TED project and their custom design of H-bridge (In Person, 4/06/20)
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
Need more analysis and technical content to validate design decisions (4/6/20, via zoom)
Calculations, including battery life
Consider safety issues when wearing the device (circuit protection) (4/6/20, via zoom)
Risks and Areas of Concern
Further delays for in coming commercial TEDs due to COVID-19
Resources or Information Required but not Available
Commercial TEDs
Schedule
Complete described goals for next week
Budget (list amount spent and amount remaining)
Spent: $265
Remaining: $1744
Progress on Report and Webpage
Completed draft on the background, existing solutions, requirements, deliverables, references, and appendix including the individual component analyses
Updated home page of project website