Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Pull out test in styrofoam is complete
Proof of concept / comparison test
CAD of winged design now includes a hinge mechanism
Parts were printed for conceptual understanding
Accomplishments from Previous Week
Completed risk reduction
Printed separate wings parts
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Have a working hinge/deployment mechanism (Helen)
Design an winged anchor without the need of a pin for a hinge (Darren, Delta, Bryan)
Individual component analysis
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Surgeon replied. Need to arrange meeting.
Need to access lab at ACTRI. Will fill out forms.
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Come up with a valid testing model
Do analysis for pin in joint
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
N/A
Risks and Areas of Concern
Deployment method
Manufacturing
Testing method
Resources or Information Required but not Available
Suture and anchor samples (may be available soon)
Schedule
Complete individual component analysis
Update Gantt chart.
Budget (list amount spent and amount remaining)
$0 spent
Progress on Report and Webpage
Research has been done for report
Progress reports and risk reduction presentation was added to website