Overview of Status of Analysis, Design, Fabrication, Tests, etc.
The project is almost finished, where the team is working on some final videos for the scalpel.
Once the amount of needed scalpel is decided, the scalpel will be manufactured.
Accomplishments from Previous Week
Took and edited video for the scalpel.
Update the second draft of the report.
Finish the project poster.
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Demonstrate the video to the sponsor for final order. (All)
Make scalpels based on needs. (All)
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Everything is good besides the cutting length and ring size. (5/23/2018 from Christina)
Action: Adjustment was made on the CAD file.
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Make good video demonstration and keep up the works. (5/23/2018 from Prof. Delson)
Action: Videos are being made for both promotional purpose and class demonstration.
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
N/A
Risks and Areas of Concern
N/A
Resources or Information Required but not Available
N/A
Schedule
Describe upcoming milestone
Update Gantt chart.
Budget (list amount spent and amount remaining)
$117 (For benchmarking)
$68(3D printing, not exceeding the free $100 budget)
$20 (Cherry tomatoes)
Remaining:
$3363