Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Solidworks models made for x and y movement.
Incorporation of low friction linear slides
Flexure designs being considered
Parts have been ordered and are shipping
Special importance to the linear slides
Accomplishments from Previous Week
Risk reduction completed
Presentation in the works
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Contact sponsors over break to setup the weekly meeting time for Spring Quarter (Sean)
Make sure parts are ordered (Razi)
Make sure important papers have been signed (Julie)
Find topics for Individual Component Analysis and start working on that (all)
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
No sponsor meeting during Final's Week or Spring Break
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Instructor suggestions/comments from presentation:
Good start
See comments inside
Nice flexure implementation
Consider taking apart an old hard-drive for examples of small and high precision flexure bearings and linear slides (in some)
Individual Component Analysis suggestions:
Squiggle motors
EDM process
Miniature bearings
Flexure bearings
Miniature gear reduction/gearbox
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
Razi/James/Dylan FILL IN HERE
Risks and Areas of Concern
Squiggle motors
Actual force output?
EDM process
Flexure implementation on a small scale
Resources or Information Required but not Available
http://www.digikey.com/product-detail/en/DK-RV-1.8-33/DK-RV-1.8-33-ND/2563772
http://innovationsupplychain.com/innovations/report.php?id=974
http://www.newscaletech.com/technology/motors-for-oem-specials.php
Schedule
Milestone:
Order parts (specifically linear slides)
Budget (list amount spent and amount remaining)
RAZI FILL IN HERE
Progress on Report and Webpage
Weekly progress reports are being updated
Webpage will be under significant revision during first and second week of Spring Quarter
The presentation and other important documents have been uploaded to the website