Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Maxon Parts ordered
Brake actuator order submitted
Mostly assembled and machined
Controls finalized
New throttle location/feasibility analyzed
Sprocket split and installed
Accomplishments from Previous Week
Split sprocket
Assembly mainly complete
Got encoder
Settled on a control scheme
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Install brake actuation - Vince
Install throttle actuation - James
Install control system - Alex
Testing, Troubleshoot and fine tune - Brian & Dian
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments
Ignore decoupling
Wants to order maxon products anyway
Actuate throttle near carburetor, rather than at the handlebars
Instructor Comments from Last Meeting and Actions Taken to Address these Comments
More clarity
Annotate CAD and CAD design considerations
Risks and Areas of Concern
Getting parts in on time
Resources or Information Required but not Available
N/A
Schedule
Testing!
Update Gantt chart.
Budget (list amount spent and amount remaining)
2500 Spent
4000 Available
Progress on Report and Webpage
Coming along