Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Considering All Design Options
Accomplishments from Previous Week
Narrowed down gear actuation
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Get recommendations from Ngiha
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments
N/A
Instructor Comments from Last Meeting and Actions Taken to Address these Comments
N/A
Goals
Gear change actuation
Stability of ATV
Reduce to 1 processor
Ethernet for IP communication
Complete steering feedback
Complete enclosing of steering mechanism
Clean up wiring
Create power supply to power everything from ATV 12V
Secondary Goals
Alternator
Anti-Roll system
Brake actuator tuning
Get a ramp response instead of step
Emergency Stop
RC/IP control
Resources or Information Required but not Available
N/A
Schedule
Present ideas to sponsorÂ
Update Gantt chart.
Budget (list amount spent and amount remaining)
No set cap.