Guidelines for Weekly Progress Reports
Weekly Progress Reports should be printed out before meetings with the sponsor and instructor.
All team members should be able to explain all items on the progress report.
To start a new progress report, create a new webpage and use the Progress Report Template.
Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Design phase is done.
All major components already ordered. In process of ordering final smaller components.
Theoretical testing is done.
Accomplishments from Previous Week
Sensors design finalized and sensors ordered: (Chris)
Set up meetings for installing water tanks to UC San Diego plumbing: (Everyone)
Checked out possible work space at Scripps with sponsor: (Everyone)
Created Risk Reduction Power Point:
Sensors: (Chris)
Coefficient of Performance (COP) and Energy Factor Calculations: (Nadim)
Water Patterns and Water Usage Data: (Cara, Xavier)
Refrigerant Analysis: (Sean)
Experimental Data/Analysis: (Sean, Chris)
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Secure components for assembly and fabrication: (Chris, Everyone)
Secure lab- meeting with Hal and Jose: (Everyone)
Start updating webpage: (Sean)
Setup plumbing/work order through Jose Moret - (Chris)
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments
Better lab area needed (cold water line needed) - currently in process of securing a new lab/work space
Instructor Comments from Last Meeting and Actions Taken to Address these Comments
N/A
Risks and Areas of Concern
Finding adequate lab area that supplies needed water patterns
Having proper plumbing installation installed in a timely manner next week so we can begin assembly
Resources or Information Required but not Available
Ground water temperatures
Water usage patterns
Schedule
Start fabrication/assembly
Budget (list amount spent and amount remaining)
$1881 + tax + shipping (sensors)
Heat Pump (purchased by sponsor)
Water Tanks (purchased by sponsor)
Above $12,000 remaining on budget
Progress on Report and Webpage
Started uploading useful material/references to the Webpage
Will start report next week