Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Dome has been cut on the CNC.
Machining complete
Jets have been fabricated and will be glued on Tuesday (today)
Sample Manifold
Complete
Casing near completion
User Interface
Everything complete except paint job
Code
Pressure gauge - requires more work
OLED screen - complete
Solenoid Valves - minor bugs
Accomplishments from Previous Week
Dome cut
Sample manifold casing
UI
Progress with UI
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Glue Dome (Dimitri - Thurs 5/31)
Attach Sample Manifold to casing (Yoav - Thurs 5/31)
UI paint job (Rudy - Wed)
Debug code (Rudy/Zhen - Friday 6/1)
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
None
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Include diode in circuit - complete.
Test manifold - awaiting code.
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
During Presentation on 5/22:
Beware of buoyancy problems with weight of dome.
Use online sources for threading strength.
Use peristaltic pump as a valve
Risks and Areas of Concern
Pressure Gauge
Code
Resources or Information Required but not Available
Thread strength for handles on dome
Schedule
Glue Dome (Wed/Thurs)
Finish housing for Sample Manifold (Fri/Sat)
Paint UI (Wed/Thurs)
Code
Fix bugs (Wed/Thurs)
Pressure Gauge (Fri/Sat)
Budget (list amount spent and amount remaining)
Spent $768
Remaining $232