Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Dome is glued!
User Interface complete
tested and functional
Sample manifold complete
tested and functional
Code
requires a little more debugging
Pressure gauge
Problems with pressure guard
Accomplishments from Previous Week
Dome glued
Excessive Testing
Code
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Possibly remove excess material from dome (Dimitri/Tom)
Debug code (Rudy/Zhen)
Also include "Flush Procedure" into code
Pressure gauge (Yoav)
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
None
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Start testing
Solve handles problem
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
None
Risks and Areas of Concern
Pressure gauge
Resources or Information Required but not Available
None
Schedule
Presentation at SPAWAR
Finish debugging code
Budget (list amount spent and amount remaining)
Spent $831 (internal)
Remaining $170
Spent $2900 (external)
Progress on Report and Webpage
It's coming along...