Installation of 32 kW Solar Array - COMPLETED! Working on next systems
Solar Install!!! March 20, 2024
Roof Joist Engineering Inspection - Oct 2023
Hallway De-Lighting Project - COMPLETED, over 200 bulbs removed. Working on LEDs
Initial calculations for 10 bulb hallway trial.
Students de-lighting hallways
As part of the Renew Our School Competition the team decided to use lux meter to set hallway lighting levels to the recommended range. Initial work showed the halls were about twice as bright as needed. The team ran trials in halls to see differences, check with students and staff for buy-in.
And within a few weeks nearly 200 bulbs have been removed, lowering our energy usage by over 4 kW-hr -- over $1,200 per year savings!
Part of Renew was using your Focus - On - Energy kit -- remember to save :)
Upcoming..... Wait and See